Hi Lakshmipathi
Actually 5th Dec'14 is yet to be processed in the system (back order). Here physically 380 was dispatched on 19th itself. However since i had set an over delivery tolerance of 10% on the net 52500 & had created 3 schedule lines, system would allow to process till the last schedule line & only in the last schedule line it would check for the tolerance criteria. Now for the first schedule line The remaining 380 would be shown as delivered qty with the second schedule line as shown below
This is the scenario replica of Production in QA. Here I can still process for another quantity 17930 as the confirmed qty is 17500, & not 380, same as order qty as well as rounded qty. Now the excess would be 380 + 430 = 810 would be carried over to last line as shown
Now total delivered qty is 35810. With 10% over delivery tolerance on 52500, I can do upto 21940. So 21940 +810 = 22750 would get reflected as shown below
Now the over delivery would be get reflected in the last schedule only as shown. Again I was able to process the delivery since confirmed qty =rounded qty=order qty=17500.
Now coming to the issue I am facing, I am not able to process the second line itself since the confirmed qty = 380 which is not equal to rounded qty & order qty as shown below
Need a way to stop this.
Regards,
jose